Great Hill Water Tank Construction, Marion, Massachusetts

This project included construction of a 1.0 million gallon, precast, pre-stressed, wire wound, concrete water storage tank in Marion, Massachusetts, with associated piping and appurtenances, a Tideflex mixing system, and site work. Other work included the decommissioning and demolition of the existing 2.0 million gallon pre-stressed concrete water storage tank at the project site. All work was completed ahead of the August 30, 2015 deadline.

Prepared tank sub-grade
Prepared tank sub-grade
Completed leveling base for tank
Completed leveling base for tank
Tank floor/footing reinforcing steel and seismic cables prior to concrete pour
Tank floor/footing reinforcing steel and seismic cables prior to concrete pour
Completed tank floor/footing
Completed tank floor/footing
Finished tank
Finished tank

Mission Critical Storage Tanks, SLVHCS, New Orleans, LA

CLIENT: NBBJ, Columbus, Ohio

PROJECT: Mission critical storage tank systems for Southeast Louisiana Veterans Health Care System (SLVHCS)

hospital new orleans
SLVHCS in New Orleans, LA

THE CHALLENGE: SLVHCS is the successor to the VA Medical Center, which was decimated by Hurricane Katrina in 2005. The new hospital requirements included green building practices and resiliency during natural disasters, including the ability to remain operational for at least five days with enough provisions and accommodations for up to 1,000 staff and patients in case of a major disaster.

The atrium of Southeast Louisiana Veterans Health Care System
The atrium of SLVHCS

THE SOLUTION: Tata & Howard provided design and construction administration services on specific components of the mission critical storage tanks, which include a domestic water tank, sewage holding tank, cooling tower process and bleed water tank, and fire protection water tank. Our design of specific components of the mission critical tanks included coating, waterproofing, mixing, pumping, bacteria control, odor control, venting, piping to five feet outside the tanks, and instrumentation and control. Specific design elements for resiliency and green design included the following:

  • Domestic Water Tank system instrumentation/controls include storage tank level measurement and control of inlet/outlet valves. The system also includes ultraviolet disinfection of all potable water pumped from the storage tank into the hospital.
  • Sewage Holding Tank is waterproof and its control system to provide automated response to an event using electrically actuated valves that direct the sewage from the gravity system to the holding tank. After the event, the system will turn the pumps on and transfer the sewage to the City’s system. A water spray system will automatically wash down the empty tank.
  • Cooling Tower Make-up Water Tank is waterproof and its control system design provides electrically actuated valves to receive rainwater from the building roof drains, condensate from the buildings, and potable water from the City’s water system. The Cooling Tower Make-up system instrumentation/controls include tank level measurement and control of inlet/outlet valves.
  • Cooling Tower Bleedwater Tank is waterproof and its control systems design provides electrically actuated valves to accept water from the cooling towers, recycles water to the cooling towers, and pumps it into the municipal sewer system. The Cooling Tower Bleedwater Tank system instrumentation/controls will include tank level measurement and control of inlet/outlet valves.
  • Fire Protection Water Tank is waterproof and its control system design provides electrically actuated valves to automate control of receipt of water from the CEP/Warehouse roof drains and the City’s water system.
  • The instrumentation and controls for all of the above elements are capable of communicating with the facility ‘s SCADA system.

PROGRESS: The new state-of-the-art facility opened on August 1, 2015, and the building is on track to receive LEED silver certification. For comprehensive information on the new hospital, please click here.

Wastewater Pump Stations, Auburn, MA

CLIENT: Town of Auburn, Massachusetts Department of Public Works

PROJECT: Replacement of three existing wastewater pump stations

wastewater pump station
The buildings are situated on very small sites

THE CHALLENGE: The sites were very small and restricted with high groundwater levels, and there were adjacent wetlands and private property. All three buildings were also very small and had other issues such as asbestos.

THE SOLUTION: We determined that the best course of action would be to demolish the buildings and convert the concrete dry pit that housed the pumping equipment into a wetwell for new, submersible pumps. The solution saved the Town hundreds of thousands of dollars.

wastewater pump stations
An existing building is inspected during the design phase

PROGRESS: Tata & Howard provided the project design and will be putting the project out to bid this summer. We will also provide construction administration when construction begins in the fall.

8.4 mgd Water Treatment Plant Design, Permitting, Construction Administration, Falmouth, MA

DAF water treatment plant

THE CHALLENGE: More stringent USEPA and MassDEP regulations, including Stage 2 Disinfectants/Disinfection-by-Product Rule (S2 D/DBPR) and the Long Term 2 Enhanced Surface Water Treatment Rule (LT2ESWTR), resulted in the Town of Falmouth needing to make a decision on whether to construct a filtration facility in compliance with the SWTR or to upgrade disinfection processes only at the existing Long Pond Water Treatment Facility (LPWTF) to maintain the existing Filtration Waiver.

THE SOLUTION: Because the existing LPWTF utilized no filtration to remove bacteria, organics, and particulates, the water quality entering the distribution system was an ongoing concern with elevated turbidity and organics leading to seasonal color, taste, and odor complaints; elevated bacteria and concentrations; and elevated algae counts. In addition, the high doses of chlorine needed to maintain the disinfection residuals required for an unfiltered supply reacted with the organics in the raw water to form disinfection by-products. Therefore, the only viable option for the Town of Falmouth was a new water treatment plant. After evaluating 22 treatment processes and developing eight treatment alternatives for pilot testing, only one treatment process met all goals: Dissolved Air Flotation (DAF) clarification, intermediate ozone followed by filtration. This alternative also scored favorably on the benefit/cost analysis.

Tata & Howard provided design and construction services for the new Dissolved Air Flotation (DAF) facility with a design capacity of 8.4 million gallons per day (mgd) for the Long Pond surface water supply for the Town of Falmouth, MA. The water treatment plant (WTP) utilizes coagulation, mixing, flocculation, dissolved air flotation (DAF), dual media filtration including granular activated carbon (GAC) above sand, chemical feed systems, and an intermediate ozone feed. Building components include HVAC, plumbing, fire sprinkler, gas and electrical services. Other work included site work with exterior piping systems, exterior above and below ground tanks, sludge holding lagoons, construction of a garage, new raw water intake and pump station, directional drilling of raw water mains, and demolition of equipment and site piping at the existing water treatment facility.

As part of the project, Tata & Howard provided design and permitting of a new 8.4 mgd intake and raw water pump station (RWPS) for the WTP.  The new intake and RWPS were constructed along the eastern shore of Long Pond and replaces the existing intake and Low Lift Pump Station.  The new intake and RWPS includes a two-level intake consisting of two 8.4 mgd rated intake screens installed at elevations -3 feet below mean sea level (MSL) and -13 feet below MSL.  The 36-inch HDPE intake pipeline connects the intake screens to the new RWPS located approximately 150 feet from the eastern shore of Long Pond.  An air burst system was designed in the RWPS to provide a means for routine cleaning of the new intake screens.

An accelerated 11 month design and permitting schedule, followed by contractor prequalification, bidding, and award, were completed in time to qualify the Town for >$3M in principal forgiveness.

Design included the following:
• 300 Drawings
• 1,200 pages of Specifications
• SRF PEF application
• Monthly project meetings
• Coordination with Building Department
• Coordination with Board of Health
• Coordination with Town IT Department
• Coordination with Police and Fire Departments
• Coordination with Gas and Electric Utilities

Permits included the following:
• Wetlands Protection Act-Local Conservation Commission
• Board of Health
• Remediation General Permit (NPDES)
• Massachusetts General Permit
• Environmental Notification Form
• Massachusetts Historical Commission: Intensive Archaeological Survey including 200 test holes
• MassDEP Approval to Construct WTP: BRP WS 24
• DWSRF PAC
• 401 Water Quality Certification
• NHESP – Turtle Protection Plan
• Chapter 91 Waterways License
• U.S. Army Corps of Engineers General Permit

The construction of the Long Pond Water Treatment Plant progressed on schedule and was completed in 2017.  dji_0051The plant included numerous sustainability and energy efficiency initiatives including the following:

  • Recycling spent backwash water to head of plant and back into the treatment process, after it passes through a plate settler to remove solids.
  • Recycling laboratory analyzer and filter influent piping gallery analyzer discharges back into the treatment process.
  • Using filter-to-waste water after a filter backwash sequence as supply water for the next backwash, instead of using finished water for backwashing.
  • Discharging cleaner supernatant water off the top of the lined lagoons to an unlined infiltration lagoon and back into the ground to minimize residuals.
  • Use of local/native plants for landscaping, including an irrigation system using collected rainwater from roof drainage.
  • Interior and exterior LED lighting fixtures.
  • Variable Frequency Drives (VFDs) on HVAC equipment and process equipment motors.

The plant went online on October 18, 2017. The work was funded under the SRF program. The Long Pond Water Treatment Plant received an ENR New England 2017 Best Project Award in the Water/Environment category, and an Associated Builders & Contractors of Massachusetts Eagle Award in the Public Works – Environmental category. For a drone video of the new water treatment plant taken by the general contractor, Methuen Construction, please see below:

SaveSave

SaveSave

SaveSave

Milford Water Treatment Facility, Milford, MA

Milford-Dilla-DAF

Tata & Howard provided construction administration, resident observation, and start-up services to the Milford Water Company for the construction of the Dilla Street Water Treatment Facility. The 5.2 mgd facility treats water from a combination of lake, river, and wells, utilizing dissolved air flotation (DAF) clarifiers and granular activated carbon (GAC) filters. The facility will replace the existing slow-sand and diatomaceous earth (DE) treatment currently utilized to treat the existing surface and groundwater sources, respectively. The facility was required to address and satisfy an Administrative Consent Order (ACO) issued by MassDEP.

Tata & Howard also completed design and oversight of a redundant cast-in-place chlorine contact tank, and has been contracted to provide engineering services for project review and construction oversight for the installation of raw water screens on intakes of both the lake and river sources. These improvements were mandated by MassDEP as part of the approval of the Dilla Street facility design.

Water Treatment Plant, Iron and Manganese Removal, Wayland, MA

WaylandMA_BaldwinWTP_aerial2

Tata & Howard completed pilot testing, design, permitting, bidding, and construction management services for the Town of Wayland’s Baldwin Pond Water Treatment Plant which included iron and manganese removal. The facility received MassDEP approval to go online and became Wayland’s first public building to receive an occupancy permit in the last 30 years. The need for the facility arose from high iron and manganese content in Wayland’s water. The facility also addressed any concern over the three Baldwin Pond wells which were under close scrutiny to determine if they were “under the influence of surface water.” The 7,500-square-foot, 1.5 million gallons per day, state-of-the-art water treatment facility was constructed to meet current and future regulations for many years ahead. The design included ozone oxidation, ultrafiltration membranes, waste recycle, and chemical feed for coagulation, pH adjustment, fluoridation, and disinfection. The treatment facility utilizes ozone oxidation and ultrafiltration to remove iron and manganese from the blended raw water from the three water supply wells.  Although other constituents are also removed through this process, the basis of this plant is to optimize the removal of iron and manganese.

The Baldwin Pond Water Treatment Facility project was highly successful through good communication and teamwork between Tata & Howard’s construction management team, the general contractor Methuen Construction, and the Town of Wayland. With less than 1% of the contingency budget applied to change orders towards the end of the project, the Town was able to do additional work. The additional work included replacing raw water mains and upgrading the existing garage onsite. A dedication ceremony for the facility was held with Representative Scott Brown, and representatives from MassDEP, Methuen Construction, and Tata & Howard joining the Town of Wayland in commemorating the completion of the facility.

SaveSave

SaveSave

Replacement Wells, Upton, MA

upton ma well replacement

Tata & Howard provided engineering services to the Town of Upton to address a water supply deficit identified in the 1998 Water Distribution System Study and the 2011 Water Master Plan and Capital Efficiency Plan™, both conducted by Tata & Howard. The multi-faceted approach was recommended to mitigate the supply deficit included maximizing their existing supply sources and the development of a new wellfield.

The original Glen Avenue Wellfield consists of two groups of 12 2½-inch diameter tubular wells, pumped through an 8-inch diameter, cast iron main. The original pumping capacity of the Glen Avenue Wellfield is approximately 0.316 million gallons per day (mgd). Recently, the yield of the Glen Avenue Wellfield has declined to approximately 0.08 mgd during the summer months. Due to the decreased yield, the Town did not have adequate supply to meet existing water demands.  Replacement wells were recommended by Tata & Howard to regain the permitted capacity of the source.

The project consisted of a test well investigation program to evaluate the feasibility of replacement wells and preliminary permitting with the Massachusetts Department of Environmental Protection (MassDEP). Once the test well program indicated that three 16” x 10”  gravel packed wells could replace the yield of the existing tubular wellfield, Tata & Howard met with MassDEP to approve the concept prior to proceeding with the pump test proposal submittal.

The scope of services included conductance of a 48 hour pump test as required by MassDEP, permitting with the MassDEP, Army Corps of Engineers, the Natural Heritage Endangered Species Program and the Upton Conservation Commission. Work also included design of well screens, submersible wells pumps, pitless adapters, variable frequency drives (VFDs), transducers in each well and water main to connect the new wellfield to the existing pump station and electrical and signal wiring. The wellfield was metered with one single meter within the pump station. Tata & Howard provided construction administration services and post construction administration services for the project.

Water Mains, DWSRF, Uxbridge, MA

Water_Mains_Construction hats

Tata & Howard is assisting the Town of Uxbridge with the design of 18,200 linear feet of 12-inch diameter water main on Route 122 from the Blackstone River to the Northbridge Town boundary. Work includes the preparation of design plans and specifications, permitting with the local Conservation Commission, MESA, and MassDOT, and the preparation of the Drinking Water State Revolving Fund (DWSRF) application, plans, and specifications checklist for the Route 122 water main design.

In addition, Tata & Howard provided design, permitting, and construction administration services for approximately 4,750 and 1,560 linear feet of 20-inch and 12-inch diameter water main, respectively, on Quaker Highway.

Water Treatment Facilities, Canton, MA

Canton MA water treatment facility

The Town of Canton had primarily been relying on water from the Massachusetts Water Resources Authority (MWRA) for a majority of its water supply needs since 2003 due to the poor water quality of their well supplies. In order to reduce the amount of water purchased from MWRA, the Town began investigations of water treatment options for iron and manganese removal. In 2005, Tata & Howard conducted a pilot test using water from Well No. 9 since it represented what was considered the worst water quality particularly with regard to iron concentration. The pilot testing indicated that oxidation with potassium permanganate followed by membrane ultrafiltration would be successful in reducing the elevated levels of iron and manganese to below the Secondary Maximum Contaminant Levels of 0.3 mg/l and 0.05 mg/l, respectively. Based on the results of preliminary pilot testing, a system from Koch Membrane Systems, Inc. (Koch) of Wilmington, Massachusetts was used.

In addition to the pilot study, Tata & Howard performed a feasibility study to determine the best location for a treatment facility for all of their well supplies. The recommended location for a single facility was a Town-owned property between Charles Drive and Pecunit Street adjacent to the Well Nos. 11 and 12 site, requiring the construction of approximately 14,500-feet of transmission main.  Due to the significant cost of the transmission mains, the disruption of traffic throughout the Town from road excavation for construction of those mains, and the unknown cost of the required permitting activities for the transmission mains, the Town decided on the construction of two treatment facilities.

Tata & Howard provided engineering design and construction administration services for two water treatment facilities. Piloting for the projects was completed at two well sites.  The Neponset Street Water Treatment Facility (WTF) has a design capacity of 2.53 mgd. The facility use ultrafiltration with chlorine dioxide for treatment. The Pecunit Street WTF has a design capacity of 0.95 mgd and uses LayneOx with chlorination for treatment. The two treatment facilities allowed the Town to reduce the volume of water purchased by the MWRA.

Water Treatment Facility, Falmouth, MA

Falmouth_Crooked_Pond_Water treatment facility

Tata & Howard completed the design of a 3.6 mgd water treatment facility which utilizes air stripping and pressure filtration technology for the removal of iron, manganese and volatile organic compounds (VOCs). The facility includes an air stripping tower, three greensand filtration units, horizontal carbon contactors, chemical storage and feed facilities, gravel pack supply well, finished water storage, and backwash holding tanks.