Water Treatment Facilities, Canton, MA

Canton MA water treatment facility

The Town of Canton had primarily been relying on water from the Massachusetts Water Resources Authority (MWRA) for a majority of its water supply needs since 2003 due to the poor water quality of their well supplies. In order to reduce the amount of water purchased from MWRA, the Town began investigations of water treatment options for iron and manganese removal. In 2005, Tata & Howard conducted a pilot test using water from Well No. 9 since it represented what was considered the worst water quality particularly with regard to iron concentration. The pilot testing indicated that oxidation with potassium permanganate followed by membrane ultrafiltration would be successful in reducing the elevated levels of iron and manganese to below the Secondary Maximum Contaminant Levels of 0.3 mg/l and 0.05 mg/l, respectively. Based on the results of preliminary pilot testing, a system from Koch Membrane Systems, Inc. (Koch) of Wilmington, Massachusetts was used.

In addition to the pilot study, Tata & Howard performed a feasibility study to determine the best location for a treatment facility for all of their well supplies. The recommended location for a single facility was a Town-owned property between Charles Drive and Pecunit Street adjacent to the Well Nos. 11 and 12 site, requiring the construction of approximately 14,500-feet of transmission main.  Due to the significant cost of the transmission mains, the disruption of traffic throughout the Town from road excavation for construction of those mains, and the unknown cost of the required permitting activities for the transmission mains, the Town decided on the construction of two treatment facilities.

Tata & Howard provided engineering design and construction administration services for two water treatment facilities. Piloting for the projects was completed at two well sites.  The Neponset Street Water Treatment Facility (WTF) has a design capacity of 2.53 mgd. The facility use ultrafiltration with chlorine dioxide for treatment. The Pecunit Street WTF has a design capacity of 0.95 mgd and uses LayneOx with chlorination for treatment. The two treatment facilities allowed the Town to reduce the volume of water purchased by the MWRA.

Water Treatment Facility, Falmouth, MA

Falmouth_Crooked_Pond_Water treatment facility

Tata & Howard completed the design of a 3.6 mgd water treatment facility which utilizes air stripping and pressure filtration technology for the removal of iron, manganese and volatile organic compounds (VOCs). The facility includes an air stripping tower, three greensand filtration units, horizontal carbon contactors, chemical storage and feed facilities, gravel pack supply well, finished water storage, and backwash holding tanks.

 

Distribution System Water Quality Study, Norwich, CT

NorwichCT_MainSt

Tata & Howard, Inc. was retained by the Norwich Public Utilities (NPU) in Norwich, Connecticut to perform a distribution system water quality study to evaluate the water age, water quality, and hydraulic gradient in the Taftville/Occum Service Area. The Taftville/Occum Service Area has high water age, due primarily to the large volume of the Occum Tank.  In addition, high levels of total trihalomethanes (TTHM) are observed throughout the Taftville/Occum Service Area.

This study examined the TTHM concentrations and high water age in the Taftville/Occum Service Area and presents various options to help mitigate these issues.

During the course of this study the following tasks were completed:

  • Updated the existing WaterGEMS hydraulic model using recent system data
  • Collected water distribution system data on current operating conditions,
    historical and current disinfection by-product samples, water age, pressures, flows, and tank levels and supply and demand data for the entire NPU system
  • Conducted a gradient evaluation of the affected service area and investigated potential alternatives to improve the current conditions, including making short and long term capital improvements to provide improved tank level fluctuation and improved customer pressure ranges
  • Performed water age modeling of the existing service area and for potential
    alternatives that improve the current conditions and graphed the results
  • Provided information and costs for alternatives to the tank passive mixing system
  • Provided recommendations for improving the service area gradient(s), water age, and water quality
  • To evaluate the Taftville/Occum Service Area, the entire NPU distribution system needed to be examined to determine the quality of the water as it enters the service area.

The key finding from this study related to the TTHM levels in the Taftville/Occum Service Area was that the formation potential in the effluent water from both of NPU’s surface water treatment plants was high enough for the TTHMs to exceed 80 µg/L at the entry point to the service area.

Based on this study, NPU has decided to add dissolved air flotation (DAF) to its Stony Brook water treatment plant. Tata & Howard designed the DAF system and other related improvements.

On-Call Water Engineering Services, Franklin, NH

FranklinNH_water treatment facility

Tata & Howard has been assisting the City of Franklin, New Hampshire with general water engineering services since 2009. The Tata & Howard team has managed several phases of work, including the design and construction of the water treatment plant and distribution system improvements.

The first phase was the design and construction of 2,500 linear feet of water main on Hill Road to connect a new water treatment plant to the City’s distribution system.  This project also involved use of four bioretention systems to treat and manage stormwater from the roadway, and was constructed in 2010.

The second phase of our work with the City included the design and construction of two parallel 2,500 LF sections of 12-inch diameter HDPE crossings beneath the Pemigewasset River using horizontal directional drilling to transport water from the City’s Franklin Falls Well to the water treatment plant site.

Tata & Howard managed the survey and geophysical studies and prepared a Preliminary Design Report and Environmental Review documents for several phases of work.  The City’s wells are surrounded by lands controlled by the US Army Corps of Engineers, which required that we complete an extensive permitting process to secure permissions for the final design of the project.

Tata & Howard completed design, construction, permitting, and funding applications for a 1,000 gallons per minute groundwater treatment plant to remove iron and manganese from three of the City’s wells. The plant has four pressure filters containing Greensand Plus media and using sodium hypochlorite for oxidation and sodium carbonate (soda ash) for pH adjustment. This plant went online July 9, 2012.

Tata & Howard provided design services for the construction of a new prestressed concrete tank at the site of an existing tank. The existing tank was in poor condition and due to the site characteristics, it was determined that construction of the new tank on the existing foundation of the old tank would be the best option.  A second tank on the site was demolished in 2013 and a new prestressed concrete tank will be constructed in its place.

Tata & Howard also conducted a full water system analysis for the City of Franklin, New Hampshire by utilizing our proprietary Capital Efficiency Plan™ methodology.  Our CEP involved creating a model of all water infrastructure in the City including sources, pump stations, treatment facilities, storage facilities, transmission, and distribution lines. Using our GIS modeling software, the system was calibrated based on fire flows in an attempt to accurately replicate the existing system. We then pinpointed deficiencies within the system based on a custom rating scale given to multiple criteria such as age, break history, material type, criticality and size. Recommendations were made for improvements in order of need. The study renewed both above ground and below ground assets. Funding for this study was in part from an Asset Management Planning Grant from NHDES.

SaveSave

Standpipe Rehabilitation, Oak Bluffs, MA

Oak Bluffs Water District, Oak Bluffs, MA

Tata & Howard has provided engineering consulting services for the design, Contract Document preparation, and bid assistance to the Oak Bluffs Water District for the interior and exterior standpipe rehabilitation of the Alpine Avenue Standpipe. We are currently providing construction administration services for the rehabilitation project.

The standpipe has a capacity of 2.0 million gallon and is a welded steel standpipe constructed in 1983. Additional work included removal of a telemetry building attached to the standpipe and design of a precast concrete building to house a tank level transmitter and communications equipment. The standpipe houses cellular carrier equipment and other communications equipment that was considered throughout the design. The Oak Bluffs water system maintains only one water storage tank. To provide adequate storage throughout the completion of the rehabilitation project an interconnection with Edgartown was opened.

Tata & Howard, Inc. coordinated the interconnection opening with the Oak Bluffs Water District, the Edgartown Water Department, and the Massachusetts Department of Environmental Protection. Oak Bluffs is a community that experiences significant demand increases throughout the summer months, therefore there was a very short window for project completion because the limiting weather conditions and increased summer demands.  The project is currently on schedule and within budget.

Unidirectional Flushing Program, Capital Efficiency Plan™, and Water Main Design, Melrose, MA

Tata & Howard provided assistance during the City’s unidirectional flushing program.  As part of the work, Tata & Howard recorded the flow from the hydrants, noted any changes in the plan, and noted any defective hydrants or valves.  When completed, a summary report outlining the total usage of water and recommended improvements to the flushing program was provided.

MelroseMAHP

Water Mains and Capital Efficiency Plan™

Tata & Howard also provided design and construction services for approximately 5,600 feet of new 8-inch water main and approximately 950 feet of new 12-inch water main throughout the City. Plans were created using available GIS data from the City and field verification. These water mains also included crossing two MWRA transmission mains and crossing the Lynn Fells Parkway. The Lynn Fells Parkway crossing required permitting with the Department of Conservation and Recreation and a traffic management plan.

This work was funded through the MWRA. As part of the project, Tata & Howard updated and verified the City’s existing hydraulic model, which has over 80 miles of water main. Work included two days of fire flow tests throughout the City and allocation of demands using up-to-date billing and parcel data. The locations of the new water mains were selected based on preliminary recommendations identified in the Capital Efficiency Plan™ that was prepared by Tata & Howard. The Capital Efficiency Plan™ identified and prioritized areas for improvement within the distribution system. Our services included evaluating the condition of the existing distribution system infrastructure to determine the adequacy of meeting present and future demands, assessing and prioritizing system improvements, reviewing and evaluating typical fire flows throughout the system, creating a pipe asset management rating system, and recommending improvements to the distribution system.

Download a whitepaper detailing a comprehensive summary of the UDF by clicking the link below:

download

Water Main and Drainage Pipe, Monson, MA

MonsonMA_watermain_drainage_pipe

This project included installation of 850 linear feet of 8-inch diameter water main, installation of 450 linear feet of new drainage, sidewalks, and roadway reconstruction on Park Avenue. The work included temporary bypass piping for the duration of the project. The project was funded by a CDBG grant.

Tata & Howard also provided engineering services for the installation of new 8-inch diameter water mains on Green Street, Lincoln Street, and Squier Avenue.  The project included the installation of drainage pipe and catch basins as well as roadway reconstruction and new sidewalks. The project was funded by a CDBG Grant.

Water Main Improvement and Design, Newton, MA

Newton, MA

newton_water_main

Since 2009, Tata & Howard has worked with the City of Newton, Massachusetts on water main improvement projects throughout the water system.  In total, the designs have included over seven miles of cleaning and lining and over eight miles of new 8-inch and 12-inch diameter water mains.

Our services have included design, completion of an Opinion of Probable Cost for construction, construction administration and resident observation. Plans were created using available GIS data from the City and field verification. The majority of the work has been funded through MWRA. A recent design included a new 12-inch diameter water main on Washington Street. Work includes cutting concrete panels, backfilling with Controlled Density Fill, and traffic management.

 

Onsite Wastewater Treatment Facility, Hopkinton, MA

Private Sector — Legacy Farms

Legacy_collage_leachfield_MSB_915v3

Tata & Howard provided design and construction administration services associated with expansion of the Legacy Farms private wastewater treatment facility and effluent disposal areas.

The project assisted in moving from 115,000 gallons per day (gpd) to 190,000 gpd, which consists of the installation of additional membrane cassettes to increase the capacity from 115,000 gpd to 150,000 gpd, installation of additional membrane modules, installation of mechanical equipment fully redundant at a maximum daily flow of 190,000 gpd, permitting assistance with MassDEP, and the construction of two additional effluent disposal areas. Construction of the first of two new effluent disposal areas is underway, and T&H Project Engineer and Certified Soil Evaluator Matt Barry was recently on-site to conduct a perc test for the second effluent disposal area.

Original Project

HopkintonMA_LegacyFarms_layoutTata & Howard provided soil investigation and evaluation, preliminary design, and design services for an onsite wastewater treatment facility and disposal system to serve the proposed Legacy Farms mixed-use development in Hopkinton, Massachusetts.

The Legacy Farms development includes a retail village, a commercial district, a variety of residential spaces (apartments, town homes, single-family homes, and multi-family structures) on approximately 733 acres currently used for nursery and agricultural uses. Approximately 940 new dwellings, 450,000 square feet of retail and commercial space, and 500 acres of restored open space will be made available by the project.

Tata & Howard’s services have included development of treatment flows for the full, built-out project, as well as selection and design of the wastewater pumping treatment and disposal systems that were compatible for the site configuration and soils, and that would provide the level of treatment required by the Massachusetts Department of Environmental Protection (MassDEP).  The challenge was satisfied by the design for a phased approach to the construction of a membrane bioreactor (MBR) treatment system, which provides a high level of treatment.

The project includes three submersible pump stations that serve the wastewater treatment facility (influent, recirculation, and effluent disposal) and two submersible pump stations within the development itself.

Disposal of treated effluent at the Legacy Farms site will be managed by a combination of conventional leaching systems and an innovative use of drip irrigation, the first large-scale application of drip irrigation for disposal of treated effluent in the State of Massachusetts.

The success of this project was related to excellent communication between Tata & Howard and the client, and a strong working relationship with MassDEP.

Pump Station Design and Wastewater Treatment Facility Upgrades, Barre, MA

Barre wastewater treatment facility

The Town of Barre retained Tata & Howard to evaluate their existing wastewater treatment facility. Tata & Howard recommended a three phase upgrade program in order to reduce the initial impact of the construction cost on the sewer use rates. Included in the upgrade program was the design and construction of a submersible pump station that lifts the raw wastewater from an equalization tank to the biological treatment process. The pump station has a capacity of 1.2 mgd and includes variable frequency drives. The pumping station is controlled by a new SCADA system at the wastewater treatment facility. Tata & Howard also designed 8,000 linear feet of collection system sewers in the Worcester Road area of town. The project also included 500 linear feet of force main and a wet well mounted pump station. The pump station has a capacity of 200 gpm.