Industrial Park Interceptor Sewer and Pump Station, Medway, MA
Tata & Howard conducted an alternatives analysis for the collection and disposal of the 80,000 gpd of wastewater anticipated from the Medway Industrial Park at full build out. The study included investigations of on site treatment and subsurface effluent disposal, intermunicipal connections, and/or a pump station with force main and gravity sewer to provide sewers to the Industrial Park. Upon completion of the study, Tata & Howard was retained to design a new sewer interceptor and pump station to service the industrial park.
Tata & Howard completed the design of 18,000 linear feet of 8-inch and 18-inch diameter gravity interceptor sewer and a dedicated pump station with force main to service the Medway Industrial Park. The pump station is a wet well mounted suction lift pump station with a capacity of 500 gallons per minute and it includes a dedicated standby generator with automatic transfer switch.