Water Treatment Facility, Water Mains, and River Crossing Horizontal Directional Drilling

directional-drilling

Tata & Howard provided design and construction services for the construction of a 1.44 mgd water treatment facility. The water treatment facility consists of a concrete block masonry building housing filtration equipment, a laboratory and office space, and associated piping, instrumentation and controls. Building components including HVAC, plumbing, and electrical services were incorporated in the facility. Other work included, but is not necessarily limited to, site work, exterior piping systems, and electrical work at an existing well pump station.

rock-drill-rig

Tata & Howard also provided design and construction services for the installation of approximately 5,000 linear feet of new 12-inch high-density polyethylene (HDPE) water main (two parallel pipes at 2,500 linear feet, each) via directional drilling beneath the Pemigewasset River, connecting the City’s Franklin Falls Well Site and the City’s Acme Well Site.

Tata & Howard provided design and construction services for the installation of approximately 2,655 linear feet of 12-inch diameter Class 52 ductile iron water main, water services, and associated valves, fittings, and hydrants on Hill Road (New Hampshire Route 3A) and a service road connecting Hill Road to the City’s Acme Well site; approximately 4,000 linear feet of 12-inch water main, water services, and associated valves, fittings, and hydrants on Lawndale Avenue, Webster Lake Road, and Kimball Street; approximately 3,200 linear feet along Lawndale Avenue; 1,200 linear feet along Webster Lake Road; and 600 linear feet along Kimball Street.  The work also included pavement restoration on Lawndale Avenue, Webster Lake Road, and Kimball Street.

The project was funded by NHDES and the USDA Rural Development office.

New Water Main, Whitinsville Water Company, MA

Tata & Howard provided engineering services for the design, construction administration, and resident project representation for the installation of approximately 3,800 linear feet of 8-inch ductile iron water main on A, B, C, D, and Border Streets for the Whitinsville Water Company. All homes in the project area are multi-family ranging from duplexes to four units per building, and are of wood construction. The area has a history of fires, so fire protection was of utmost concern.

The project began in February of 2016. Each home had its water service replaced, and also received a 6-inch ductile iron water main that was installed with a gate valve and a cap so that the homeowner could install individual fire and water services to each unit. For example, the homes with four units could be tapped with eight new service lines, giving each home a fire service and a water service and increased protection from fire. As added fire protection, Tata & Howard also replaced all hydrants and added four additional hydrants to the project area.

All water main installation was completed in November of 2016, and final paving took place in the spring of 2017.

Bliss Street Water Main, Northampton, MA

Bliss Street in Northampton, MA had experienced several water main breaks. Therefore, the City wanted the main to be replaced over the winter rather than waiting until spring. The project included design, bidding, and construction administration services for the water main replacement on Bliss Street from Scanlon Avenue to Willow Street. The design included new 8-inch diameter ductile iron water main, services, and appurtenances, as well as preparation of base plans from available City records, City GIS mapping data, and field measurements.

Construction occurred during the winter to meet the client’s schedule.  Two change orders were issued to address hydrant extensions and sewer component repairs. The bid opening was the day before Thanksgiving. Construction started in December and was substantially completed by spring.

 

Raw Water Transmission Main Replacement in Stamford, CT

awc-laurel-street-raw-water-main

Owner: Aquarion Water Company, Shelton, Connecticut

Tata & Howard provided professional engineering services for surveys and mapping; subsurface explorations; preliminary and final design; bidding; and construction phase services, including resident project representation, for the partial replacement of Laurel Reservoir Raw Water Transmission Main located on Lakeside Drive in Stamford, CT. The main was replaced after a history of multiple pipe failures.

This project included replacing approximately 3,670 feet of an existing 13,540 feet of 42-inch diameter prestressed concrete cylinder pipe (PCCP) used to transfer raw water by gravity from Laurel Reservoir to the Stamford Water Treatment Plant (WTP). The pipe was replaced with 48-inch Class 52 ductile iron pipe.  Three existing 8-inch blowoffs and two existing 4-inch diameter automatic air release valves in this section of main were replaced and upsized with new 12-inch diameter blowoffs and 12-inch diameter valves. The main was encased in concrete at three culvert crossings. Additionally, two 24-inch diameter access openings were installed in the existing 42-inch diameter main that was not being replaced to allow for inspections while the pipe was drained and out of service.  The project also included replacement of four existing automatic air release valves on the existing 42-inch diameter PCCP that was to remain in service.

Interceptor Sewer, Danbury, CT

interceptor_sewer
Jacking a 48-inch steel casing under I-84 in Danbury, CT

The Oakland Avenue sanitary sewer project consisted of jacking a 48-inch steel casing pipe through the Interstate-84 embankment in Danbury, CT and installing a new 24-inch sanitary sewer to replace the existing 16-inch sewer that is undersized. The project alleviated the restriction that is causing sewer overflows. Services included surveys and mapping, review of easements, review and updating of original design, preparation of plans and specifications, bidding, construction administration, and resident observation. The new sewer line installation will complete an interceptor project that was constructed in 1994.

Construction was completed in 2016.

FEMA Hazard Mitigation Grant in MA

FEMA grant
The exposed water main ran under the bridge on Mechanic Street

Tata & Howard provided engineering consulting services to the Town of Monson, Massachusetts for the relocation of the 8-inch diameter water main on Mechanic Street.

The main was originally constructed in 1897 under the streambed; however, after 117 years in this location, the decrease in surface water elevation had exposed the water main. The water level averaged about one inch below the top of pipe, exposing the top portion of the entire section of main that crossed the brook, approximately 15 linear feet of main. Exposure of the water main made it susceptible to freezing during the winter months, which could have resulted in a break and subsequent lost water or contamination from the brook to the Town’s entire water system, potentially resulting in significant costs to residents and to repair, clean, and disinfect the system. The main provides potable water to approximately fifty residents. There were only two gate valves located at the ends of Mechanic Street. As a result, if the main were to fail at the bridge, the entire street would have to be shut down in order to repair the damage, disrupting water service for the 50 serviced residents.

The Mechanic Street Bridge has a history of failure. As a result of a major flood event in 1955, the bridge failed and was completely replaced in 1956. The bridge ran directly over the water main, which posed an additional threat to the main should the failure reoccur. Although the main was unaffected during the previous failure, its weakened condition made it more susceptible to failure in a similar event.

Tata & Howard provided funding assistance and the project qualified for and received a FEMA Hazard Mitigation Grant for 75% of the cost of the project. The work included the preparation of design plans and specifications for the relocation of the 8-inch water main to a self-supporting beam structure attached to the bridge abutments on Mechanic Street. The project also included bidding, permitting, construction administration, and resident observation.

Water Mains, Milford Water Company, MA

water_main_construction

Tata & Howard was contracted to design approximately 2,000 linear feet of new 12-inch diameter ductile iron water main on Congress Street and West Fountain Street (High Service Area). The work included borings, survey, preparation of plans and specifications, and bidding. Construction of the High Service Area Water Mains took place over the summer, and was recently completed. Tata & Howard provided construction administration and resident observation services.

In addition, Tata & Howard was contracted to design approximately 2,400 linear feet of new 12-inch diameter ductile iron water main on East Main Street (Route 16). The work included survey, wetlands delineation, MassDOT permitting, completion of a Notice of Intent, preparation of plans and specifications, bidding, construction administration, and resident observation services.

Water Mains, DWSRF, Uxbridge, MA

Water_Mains_Construction hats

Tata & Howard is assisting the Town of Uxbridge with the design of 18,200 linear feet of 12-inch diameter water main on Route 122 from the Blackstone River to the Northbridge Town boundary. Work includes the preparation of design plans and specifications, permitting with the local Conservation Commission, MESA, and MassDOT, and the preparation of the Drinking Water State Revolving Fund (DWSRF) application, plans, and specifications checklist for the Route 122 water main design.

In addition, Tata & Howard provided design, permitting, and construction administration services for approximately 4,750 and 1,560 linear feet of 20-inch and 12-inch diameter water main, respectively, on Quaker Highway.

Capital Efficiency Plan™ including Water System Master Plan, Northampton, MA

NorthamptonMA_key_bridge

Tata & Howard has completed a Water System Capital Efficiency Plan™ for the City of Northampton.  The plan includes a comprehensive water system master plan that evaluates the hydraulics of the system as well as critical components and asset management considerations. The hydraulic analysis included completion of fire flow testing and c-factor tests. Tata & Howard developed a hydraulic model from the City’s extensive ArcGIS database and the flow test results were used in verification. Tata & Howard reviewed recommended static pressures and Insurance Service Office recommended fire flows as well as estimated needed residential and commercial fire flows throughout the system.

The Northampton water system has wide range of ground elevations, resulting in extreme high and low static pressures in some areas. To maintain recommended system pressures, a new service zone was recommended to divide the distribution system. The recommendations included a new water storage tank, pressure reducing valves and transmission main improvements. Tata & Howard also developed additional recommended water main improvements to meet fire flow needs.

The asset management portion of the project included a detailed analysis of each segment of pipe in the water system based on age, diameter, material, pressure, soil conditions, break history, and potential water hammer. Each segment of pipe was given a numeric rating based on weighted asset criteria developed in cooperation with the City. This information was used with the hydraulic evaluation and critical component assessment to determine the prioritized improvements for the system.

Tata & Howard is also assisting the City with testing of pipes throughout the system. The work includes visual evaluation of samples and pipe strength testing. An analysis of the estimated service factor of each pipe segment will be provided to the City and used to supplement the information obtained during our asset management analysis.

District Water Treatment Facility, Transmission Mains, and Metering Station, Mattapoisett, MA

MRVWD_water treatment facility

The MRVWD water treatment facility project was designed to treat water from eight wells belonging to the Towns of Fairhaven, Marion and Mattapoisett.  The MRVWD facilities also include approximately 5 miles of raw water transmission mains between the wells and the water treatment facility, finished water transmission mains from the water treatment facility to the existing town transmission mains, six new 100 HP high lift pumps and control/metering stations. The existing pump stations were upgraded to pump water to the water treatment facility but operation of the pump stations will remain the responsibility of the individual towns.

The total cost of all project components was approximately $16.5 million, which was partially funded with a low interest SRF loan. By constructing a regional facility, the towns were able to save over $4.9 million in design and construction costs in comparison to individual treatment facilities.