
The Happy Hollow Chemical Feed Station design consisted of a small chemical feed building and equipment, well pump and water main installation, and associated utilities and site work. The only impervious surface on the site was the new building. Since building roof was a membrane and not metal and there was no paving, MassDEP guidelines allowed for direct infiltration of the stormwater runoff from the roof. This was accomplished by pitching the roof to one side and collecting the runoff into two 4” PVC drain pipes that discharged into an infiltration system consisting of four Cultec infiltration chambers.
Since it was not feasible to install an overflow for these chambers, the infiltration system was designed based on a 100-year storm event in order to have the capacity to collect, store, and infiltrate the largest storms that the site could potentially encounter. The chemical feed building also housed a re-agentless chlorine analyzer that required a constant supply of sampling water and therefore produced a constant waste flow of clean water. This analyzer waste flow was also included in the sizing of the infiltration system.

Tata & Howard has provided the Town of Grafton, MA with extensive stormwater field engineering services. Services have included the completion of stormwater infrastructure mapping in accordance with the Massachusetts NPDES MS4 Permit, Illicit Discharge Detection and Elimination Program. Mapping services included outfalls and interconnections, manholes, catch basins piping, and establishment of catchment areas. Follow-up work will continue with outfall inspection, screening, and dry weather sampling.

Tata & Howard provided engineering services for Marlborough, MA for a redesign of the Town’s Public Works Facility. The work included a stormwater management design and program to reduce the contamination of stormwater runoff and prohibit illicit discharges as required by current regulations and as required by the latest draft MS4 permit.
The project also included a proposed site plan showing the proposed drainage improvements for the site including new drainage system infrastructure, stormwater detention and treatment facilities, existing and proposed grade, and all building and features. The project also included an erosion control plan and drainage report appropriate for various environmental permitting submissions including and erosion control plan with boundaries of any resource areas and associated buffers. Lastly, Tata & Howard assisted with permitting assistance and obtaining Conservation Commission approval of the project.
Tata & Howard provides ongoing stormwater engineering services to the Town of Leicester, Massachusetts in support of their status as a NPDES Phase II Municipal Separate Storm System (MS4) community. Work involves outfall mapping and inspection, illicit discharge detection and elimination, development of annual reports, and compliance with documentation and reporting components of the MS4 Permit.
In addition, Tata & Howard assisted the Town of Leicester Highway Department with mapping and inspection of stormwater outfalls and produced a unique record of each outfall including photographs. Tata & Howard also developed a report summarizing the outfall inspections.

Tata & Howard provided construction administration, resident observation, and start-up services to the Milford Water Company for the construction of the Dilla Street Water Treatment Facility. The 5.2 mgd facility treats water from a combination of lake, river, and wells, utilizing dissolved air flotation (DAF) clarifiers and granular activated carbon (GAC) filters. The facility will replace the existing slow-sand and diatomaceous earth (DE) treatment currently utilized to treat the existing surface and groundwater sources, respectively. The facility was required to address and satisfy an Administrative Consent Order (ACO) issued by MassDEP.
Tata & Howard also completed design and oversight of a redundant cast-in-place chlorine contact tank, and has been contracted to provide engineering services for project review and construction oversight for the installation of raw water screens on intakes of both the lake and river sources. These improvements were mandated by MassDEP as part of the approval of the Dilla Street facility design.

Tata & Howard completed pilot testing, design, permitting, bidding, and construction management services for the Town of Wayland’s Baldwin Pond Water Treatment Plant which included iron and manganese removal. The facility received MassDEP approval to go online and became Wayland’s first public building to receive an occupancy permit in the last 30 years. The need for the facility arose from high iron and manganese content in Wayland’s water. The facility also addressed any concern over the three Baldwin Pond wells which were under close scrutiny to determine if they were “under the influence of surface water.” The 7,500-square-foot, 1.5 million gallons per day, state-of-the-art water treatment facility was constructed to meet current and future regulations for many years ahead. The design included ozone oxidation, ultrafiltration membranes, waste recycle, and chemical feed for coagulation, pH adjustment, fluoridation, and disinfection. The treatment facility utilizes ozone oxidation and ultrafiltration to remove iron and manganese from the blended raw water from the three water supply wells. Although other constituents are also removed through this process, the basis of this plant is to optimize the removal of iron and manganese.

The Baldwin Pond Water Treatment Facility project was highly successful through good communication and teamwork between Tata & Howard’s construction management team, the general contractor Methuen Construction, and the Town of Wayland. With less than 1% of the contingency budget applied to change orders towards the end of the project, the Town was able to do additional work. The additional work included replacing raw water mains and upgrading the existing garage onsite. A dedication ceremony for the facility was held with Representative Scott Brown, and representatives from MassDEP, Methuen Construction, and Tata & Howard joining the Town of Wayland in commemorating the completion of the facility.

SaveSave
SaveSave

Tata & Howard provided engineering services to the Town of Upton to address a water supply deficit identified in the 1998 Water Distribution System Study and the 2011 Water Master Plan and Capital Efficiency Plan™, both conducted by Tata & Howard. The multi-faceted approach was recommended to mitigate the supply deficit included maximizing their existing supply sources and the development of a new wellfield.
The original Glen Avenue Wellfield consists of two groups of 12 2½-inch diameter tubular wells, pumped through an 8-inch diameter, cast iron main. The original pumping capacity of the Glen Avenue Wellfield is approximately 0.316 million gallons per day (mgd). Recently, the yield of the Glen Avenue Wellfield has declined to approximately 0.08 mgd during the summer months. Due to the decreased yield, the Town did not have adequate supply to meet existing water demands. Replacement wells were recommended by Tata & Howard to regain the permitted capacity of the source.
The project consisted of a test well investigation program to evaluate the feasibility of replacement wells and preliminary permitting with the Massachusetts Department of Environmental Protection (MassDEP). Once the test well program indicated that three 16” x 10” gravel packed wells could replace the yield of the existing tubular wellfield, Tata & Howard met with MassDEP to approve the concept prior to proceeding with the pump test proposal submittal.
The scope of services included conductance of a 48 hour pump test as required by MassDEP, permitting with the MassDEP, Army Corps of Engineers, the Natural Heritage Endangered Species Program and the Upton Conservation Commission. Work also included design of well screens, submersible wells pumps, pitless adapters, variable frequency drives (VFDs), transducers in each well and water main to connect the new wellfield to the existing pump station and electrical and signal wiring. The wellfield was metered with one single meter within the pump station. Tata & Howard provided construction administration services and post construction administration services for the project.
Tata & Howard provided engineering services to the University of Southern Maine related to the interior and exterior rehabilitation of a welded steel water storage tank. The standpipe was constructed in the 1950’s and is approximately 30 feet in diameter and 105 feet tall with a capacity of 0.55 million gallons. The scope of services included preparing Contract Documents for the cleaning, interior abrasive blasting, exterior pressure washing, and interior and exterior coating application.
The project also included coordination with two cellular companies and incorporation of corresponding design considerations into the Contract Documents. Additional design considerations included providing the USM logo on the tank exterior, repairing foundation cracks and gaps, extending the overflow pipe and installing a flapper, screen, and concrete splash pad, providing safety climb system for exterior access ladder, replacing the roof vent, and installing a new roof access hatch. Tata & Howard provided bid assistance, construction administration services, and full time construction observation. Since the standpipe is located on a college campus, the time frame for completion was limited to summer break, but the standpipe rehabilitation project was completed within budget and on schedule.

Tata & Howard assisted the Town of Winchester to meet the Collection, Management, Operation, and Maintenance (CMOM) requirements in the Town’s NPDES General Permit. The work consisted of the preparation of an outline for the Full Collection System Operation and Maintenance Plan, which included descriptions of staffing, management goals, information management, condition assessment, recent studies, and construction activities. Tata & Howard was also retained to prepare the Full Collection System Operation and Maintenance Manual, which included updating the outline, preparing a preventative maintenance and monitoring program, identifying sources of suspected overflows and back-ups, preparing a program for preventing I/I related effluent violations, and a public outreach program regarding I/I control.
Additionally, Tata & Howard has assisted the Town of Winchester with three phases of improvements to the Winchester Wastewater Treatment Facility (WWTF), I/I investigations, repair and rehabilitation of the sewer collection system to remove I/I, and securing funding to upgrade the WWTF and sewer collection system.

Tata & Howard provided engineering services for the evaluation, design, and construction of approximately five miles of pressure and gravity sewer to serve the mountain resort community of Jay, Vermont. The design also included the upgrade to air release structures for 4.5 miles of force main and upgrade of two pump stations, one a progressive cavity station.
In addition, Tata & Howard provided engineering services including planning, evaluation, design, permitting and construction services for the Troy-Jay wastewater treatment facility upgrade. The new headworks facility included screening and aerated grit removal and influent design for the force main/pressure sewer from the two towns and mountain resort. The treatment process was an SBR facility with tertiary filtration and UV disinfection for phosphorus removal.