Burbank Tank Rehabilitation – Millbury, MA

The Burbank Tank is a 110-year-old buried fieldstone tank located in Millbury, MA.  Due to concerns from MassDEP on the age and condition of the tank, the Aquarion Water Company contracted Tata & Howard to provide design specifications and DN Tanks was selected as the tank rehabilitation contractor for installing shotcreting lining to the fieldstone walls, pouring a new concrete floor and removing pipes within the tank that are no longer in use.  While the proposed work is not a structural fix for the tank, shotcreting the walls will reduce potential root intrusion, seal up areas of lost mortar, and reduce the potential for leakage.  The rehabilitation was undertaken in early 2017 and completed in 8 weeks.

The Burbank Tank is the only storage tank in the water distribution system.  Therefore, careful planning and evaluation of the system using the hydraulic model was required to review the options for operations without storage for an extended period of time.

WWTP Evaluation, Manchester-By-The-Sea, MA

Tata & Howard completed a comprehensive evaluation of the Manchester-by-the-Sea wastewater treatment plant (WWTP).

The Manchester-the-Sea WWTP was originally constructed in 1998. The plant is designed to treat an average daily flow (ADF) of 1.20 mgd. The plant includes the following treatment processes: influent pumping, influent sewage grinding, manual bar rack, grit removal equipment, aeration tanks and blowers, clarifiers, chlorine disinfection, and sludge thickening.  The treated effluent is discharged into the ocean with effluent pumps through an ocean outfall pipe.

The treatment plant evaluation included a comprehensive assessment of the physical condition of the plant to provide an additional 20-year life for the facility.  The evaluation included all mechanical systems and equipment, electrical systems and controls, buildings, and structures.  The study included an evaluation of energy usage at the plant and developed recommendations to improve energy efficiency including replacement of influent and effluent pumps, and aeration blowers to better match plant flow requirements and system demands.

The final report includes an evaluation of existing conditions and proposed recommendations to improve current operations, upgrade aging equipment and facilities, improve energy efficiency,  and provide plant hardening against potential climate change and sea level rise.

 

Worcester, MA Hydraulic Modeling and Capital Efficiency Plan™

Tata & Howard completed a hydraulic model update and Capital Efficiency Plan™ for the City of Worcester. As part of the project, Tata & Howard updated and verified the City’s existing hydraulic model, which has over 550 miles of water main. Work included three days of fire flow tests throughout the City and allocation of demands using up-to-date billing and parcel data. Phase II of the project, the Capital Efficiency Plan™, identified and prioritized areas for improvement within the distribution system. Our services included evaluating the condition of the existing distribution system infrastructure to determine the adequacy of meeting present and future demands, calculating needed storage requirements, assessing and prioritizing system improvements, reviewing and evaluating typical fire flows throughout the system, creating a pipe asset management rating system, and recommending improvements to the distribution system.

Tata & Howard calibrated the hydraulic model under extended period simulation for an evaluation of the Super High Service Area with the Chester Street Tank off-line due to rehabilitation. The configuration of the service area included two distinct zones. The Chester Street Tank is located in one area and the Howland Hill and Apricot Tanks are located in the other area. To remove the Chester Street Tank from service, an evaluation of supply and pressures needed to be completed. The results of the analysis included running both zones off the Apricot Tank and utilizing the Chester Street Pump Station to maintain pressures within the vicinity of the Chester Street Tank.

Water Audit, Water Meter and Advanced Meter Infrastructure (AMI) Evaluation, Wayland, MA

Tata & Howard, Inc. was retained by the Town of Wayland, MA to complete a water audit of the water distribution system based on data and system information for the calendar years 2013, 2014, and 2015. The project included assessing the amount of lost water using the American Water Works Association M36 water audit methods. The report estimates the volume of lost water in terms of non-revenue water, identifies potential sources of lost water, and estimates system performance indicators including the Infrastructure Leakage Index.

The AWWA water audit results found that the Town’s non-revenue water by volume was approximately 46.4% in 2013, 20.5% in 2014, and 18.5% in 2015. The associated annual costs of water lost were approximately $425,000 in 2013, $320,000 in 2014, and $398,000 in 2015. In addition, 64% of the Town’s meters are over 15 years old.

Recommendations to reduce water loss included the following: volumetrically testing master meters at multiple flow rates and performing a field to database audit of SCADA flow reported from master meters; implementation of a customer meter testing and replacement program; and documentation of unbilled and unmetered water use with the use of meters whenever possible.

To address the aging meters, Tata & Howard completed a water meter and advanced meter infrastructure (AMI) evaluation. The project included an evaluation of water meters, automatic meter reading (AMR) systems, and advanced metering infrastructure (AMI) systems for the Town of Wayland’s water distribution system. The purpose of the evaluation was to compare different AMR/AMI technologies to assist in the selection of a new meter reading system to provide a recommendation for AMR/AMI technology to best suit the needs of the Town.

Following the meter evaluation, Tata & Howard provided assistance with a request for proposal (RFP) for new water meters and AMI system including specifications and proposal evaluation criteria. Tata & Howard is currently providing assistance during the implementation of the AMI system and the installation of the water meters and RF endpoints for the Town of Wayland.

SaveSave

SaveSave

Water Audit, Grafton, MA

Tata & Howard, Inc. was retained by the Town of Grafton, MA to complete a water audit of the water distribution system based on data and system information for the calendar year 2015. The project included assessing the amount of lost water using the methodology outlined in AWWA’s Water Audits and Loss Control Programs, Manual of Water Supply Practices – M36, Fourth Edition, published in 2016. The final report estimates the volume of lost water in terms of non-revenue water, identifies potential sources of lost water, and estimates system performance indicators including the Infrastructure Leakage Index.

The AWWA water audit results found that the Town had total water losses of approximately 182 million gallons in 2015 and the associated annual cost of water lost was over $312,000.  Of this, 11% is Unavoidable Annual Real Losses (UARL). Recommendations to reduce water loss include volumetrically testing master meters and performing a field to database audit of SCADA flow reported from master meters and interconnections, beginning a customer meter testing and replacement program, documenting unbilled and unmetered water use with the use of meters whenever possible, and conducting a third-party review of the leakage detection program. The estimated cost of recommended improvements to the District’s water loss control program was $20,000 for the SCADA audit and leakage detection program review, $129,000 to replace customer meters over 25 years old, and $7,000 in annual costs for establishing master meter and customer meter testing and replacement programs. Implementation of all recommendations would result in an expected ROI of less than one year.

Trinity Avenue Pump Station, Grafton, MA

Tata & Howard is providing engineering services to the Grafton Water District for the Trinity Avenue Pump Station at the Trinity Avenue Wellfield. The project included permitting, design, and bidding of the pump station as well as providing assistance with permitting, design, and reporting to the Massachusetts Department of Environmental Protection (MassDEP) for the proposed Trinity Avenue Well site. The property was owned by the Massachusetts Division of Fisheries and Wildlife (DFW).

The Grafton Water District swapped land with the DFW to obtain ownership and control of the Trinity Avenue site.  Test wells were installed and short term pump tests were completed on each of the wells. Based on the results of the tests, it was recommended to install a three well configuration of 18 inch x 12 inch gravel packed wells resulting in approximately 800 gallons per minute (gpm).

The project included an evaluation of alternatives for the access road including installation of a bridge or an open bottomed culvert, and T&H assisted with the preparation of permanent easements for the installation of utilities and roadway to the well site. In addition, T&H prepared and submitted an NOI to the Grafton Conservation Commission. Design included double wythe block and interior concrete painted block with wood truss roof and asphaltic shingles; and security included chain link fence, gates, locks, intrusion alarms, and lighting. T&H also assisted with the coordination of the installation of three phase power to site. Chemical feed at the station includes KOH for pH adjustment and chlorine gas for disinfection. Standby power was included in an outdoor enclosure. The design also included a 24-inch transmission main for 4-log removal.

 

SaveSave

Canaan, VT and Stewartstown, NH Energy Efficient Wastewater Treatment Plant Upgrades

The Towns of Canaan, Vermont and Stewartstown, New Hampshire operate a shared wastewater treatment facility, which required significant upgrades. The existing facilities were 40 years old and although a few upgrades were performed in the 90s, the facilities were not performing well, did not meet Life Safety codes, and required significant maintenance. The upgrade met all of the goals of the Client by providing for simple operation and maintenance requirements, meeting the Life Safety codes, eliminating confined spaces, lowering of electrical power costs, and meeting discharge parameters through production of high quality effluent. The solutions developed for the upgrade to this facility were also economical.

Control building insulated concrete forms

One of the primary elements of the design was the consideration of the economics of energy reduction. The design incorporated insulated concrete form construction for the building walls with R-49 insulation rating in the ceilings.  The design also included a wood pellet boiler with a pellet silo and hot water heating system, which allowed for reduction of explosion proof heaters in the headworks building. All of the windows were low-E and highly insulated, and an outer glassed-in entry way increased the solar gain retention of the building and reduced heat loss.  he process headworks and operations buildings were constructed as single story structures, increasing operator safety.

The lagoon aeration system is now a fine bubble, highly efficient process with additional mixing provided by solar powered mixers that help reduce aeration requirements, improve treatment, and allows for the addition of septage, all at no cost due to solar power. The pump station upgrades were designed to eliminate daily confined space entry by the operator by the conversion to submersible pumps. For sludge removal, a unique and simple “Sludge Sled” system was incorporated, which allows the operators to easily remove the sludge at their convenience. Sludge treatment is accomplished with a geo-bag system that allows the sludge to be freeze dried, reducing the volume by almost 50% with no energy consumption.

The influent pump station was designed with three pumps instead of the normal two-pump system in order to meet both present and future design flows, allow for lower horsepower pumps, improve flexibility, reduce replacement costs, and reduce energy costs. The other four deep dry pit pump stations were converted to wet wells and submersible pumps, eliminating confined spaces, and are equipped with emergency generators, eliminating the need for operator attention when power is lost.

Solar mixers for lagoons

The incorporation of highly energy efficient building components resulted in reducing annual operation and maintenance costs, which resulted in lower user rates and a more sustainable facility. All building components are virtually maintenance free.  All of the equipment and processes were selected to reduce both annual and future replacement costs.

The treatment system is a 3-cell aerated lagoon system, and the solar powered mixers were installed to enable reduction of the aeration needs and horsepower during the summer months when septage is added.  The aeration blowers, which are housed in insulated enclosures, reduce noise and were sized to allow for the addition of septage to the lagoons, which is not common in Vermont. The aeration blowers are controlled with Variable Frequency Drives (VFDs), which allow for greater operator control of aeration and provide energy cost savings. The operation is simple and safe for operators and others who need to maintain the facility and equipment. The design has provided flexibility to the operators and has resulted in an energy efficient, sustainable solution for this community.


 

 

Read the whitepaper here.

 

 

SaveSave

SaveSave

SaveSave

Ozone Water Treatment Plant in Franklin, MA

Tata & Howard provided design and construction services for a new water treatment facility that houses a 1.2 mgd ultrafiltration system and completed a pilot test that consisted of an evaluation of two separate ultrafiltration technologies. Franklin Wells No. 1 and 2, located off Hayward Street in Franklin, Massachusetts were installed in the 1940’s with a combined safe yield of 1.2 million gallons per day. Due to high concentrations of iron and manganese in the groundwater, the wells were only used to meet peak water demands during the summer months. The construction of the water treatment facility recaptures the yield from these two sources.

The water treatment facility consists of a main building which houses static mixers, ozone feed equipment, chemical feed equipment, prefilters, membrane filtration equipment, instrumentation and controls. Treatment consists of ozone oxidation followed by membrane ultrafiltration. The project was funded in part by the Massachusetts Water Pollution Abatement Trust through a low interest state revolving fund loan.

The overall treatment scheme is as follows: ozone injection, oxidation of iron and manganese in an ozone contact tank, prefiltration, treatment through two ultrafiltration membrane skids, chlorination prior to a clearwell, and fluoride addition prior to discharge into the distribution system. The plant is designed to recycle backwash water and membrane recirculation water to the head of the plant utilizing two decant tanks. Ozone is produced on site utilizing compressed air, while a LOX tank is available to allow for the production of additional ozone if required in the future.

 

Capital Efficiency Plan™ for Manchester-By-The-Sea, MA

Tata & Howard, Inc. was recently retained by the Town of Manchester-by-the-Sea to complete a Capital Efficiency Plan for the Town’s water system. The system was evaluated to identify areas of the water distribution system in need of rehabilitation, repair, or replacement, and to prioritize improvements to make the most efficient use of the Town’s capital budget. The study evaluates the existing water infrastructure including water transmission and distribution piping and appurtenances. In addition, water storage and supply needs were evaluated and prioritized.

The analysis and improvements in this report are based on the Three Circles Approach for optimum capital efficiency, which combines hydraulic and critical component considerations with an asset management rating system to evaluate the condition of the water mains in the distribution system. Each circle represents a unique set of evaluation criteria for each water main segment.  From each set of criteria, system deficiencies are identified. System deficiencies from each circle are then compared. Any deficiency that falls into more than one circle is given higher priority than one that does not.

\Using the Three Circle Approach, recommended improvements will result in the most benefit to the system. In addition, the Three Circle Approach allows us to identify any situations that mitigate a deficiency in one circle and eliminate a deficiency in another circle. By integrating all three sets of criteria, the infrastructure improvement decision making process and overall capital efficiency are optimized.

Recommendations included a siting study for a second storage tank, Phase I-III distribution system improvements, and the continuance of scheduled maintenance programs such as hydrant flushing, leak detection, and meter testing. The Town’s pavement management plan was also taken into consideration to best prioritize and coordinate utility work with roadway reconstruction.

 

SaveSave

SaveSave

Capital Efficiency Plan™ and Water Supply Study in Rowley, MA

A Capital Efficiency Plan was completed for the Town of Rowley in May 2017.  The study evaluated the 45 miles of the Town’s water distribution system using the Three Circles Approach, which consists of a system hydraulic evaluation, criticality component assessment, and asset management considerations. From each set of criteria, system deficiencies were identified and a 20-year recommended improvements plan was provided. Recommended improvements consisted of water main replacement projects, a pumping capacity evaluation and well redevelopment study, an interconnection analysis, and a distribution static pressure evaluation.