Wastewater Pump Station Rehabilitation, Milford, MA

MilfordMA_wastewater_treatment_plant_aerial

Tata & Howard provided all design and construction services related to a treated wastewater pump station at the Town’s advanced wastewater treatment facility.  This station has a capacity in excess of 1 mgd and is used to pump treated wastewater to a gas turbine power generation facility where it is used for cooling water.  Included in this project was the preparation of plans and specifications and the monitoring of water quality effects on the Charles River.

The Birch Street Pump Station is a submersible pump station consisting of two 700 gallons per minute pumps. Under maximum day flow conditions, the station has operated well above its current capacity and pump run times of 24 hours have been recorded. Therefore, prior to accepting additional flows would require upgrades to be completed. In 2013, Tata & Howard worked with the Town of Milford and was retained by a developer to design proposed upgrades for the Birch Street Pump Station rehabilitation which included upgrades to the existing submersible pumps, electrical and instrumentation, and controls.

Sewer Improvements and Wastewater Pump Stations, Bingham, ME

Bingham ME wastewater pump station

Tata & Howard provided engineering services associated with sewer improvements including evaluation, design, and construction of 3,500 linear feet of interceptor sewer, 2,500 linear feet of force mains, and three pump stations. In addition, Tata & Howard provided design and construction of 5,000 linear feet of interceptor sewer, 4,000 linear feet of gravity sewer including a river crossing, and a pump station. Tata & Howard also provided design and construction services for three new wastewater pump stations. The pump station scope included upgrading of one pump station and the design of two other pump stations. One of the pump stations is a suction lift station while the other two are submersible stations.

Wastewater Pump Station, Franklin, MA

FranklinMA_wastewater treatment facility interior

Tata & Howard was retained by the Town of Franklin to evaluate the wastewater pump station that serves the Franklin Industrial Park. The pump station had been experiencing capacity issues and periodic overflows. The design by Tata & Howard included the replacement of two existing wastewater pumps with 350 new gpm capacity pumps with variable frequency drives. The project also included a substantial increase in the volume of the station’s wet well through the construction of additional precast concrete tanks. The work also included upgrades to the existing alarm and communications systems.

Water Main Replacement, Auburn, MA

Phase I services included engineering services for bid, award, construction administration and resident observation services for approximately 6,500 linear feet of 12-inch water main and 750 linear feet of 8-inch diameter water main for a water main replacement project on Packachoag Street.

Phase II services included engineering design, bid and award, and construction administration and resident observation services for approximately 5,000 linear feet of 8-inch water main. Both phases are funded by the USDA Rural Development program.

Wastewater Pump Stations and Treatment Plant, Canaan, VT

Canaan VT aerial

Tata & Howard provided engineering services for the evaluation, permitting, design, and construction of five wastewater pump stations. The pump stations included a new triplex pump station with valve structure. The wastewater treatment plant upgrade was in addition to the pump stations. The other four pump stations consisted of a new, completely relocated pump station and the upgrading of three other dry pit wet pit stations to include generators and controls for telemetry. The pump station design included a plan for maintaining operations of the stations throughout construction, which was completed in the fall of 2014.

Wastewater Treatment Facility, Hopedale, MA

HopedaleMA_wastewater treatment facility disk filter

Tata & Howard has been working with the Town of Hopedale, Massachusetts for a number of years on a variety of wastewater collection and treatment projects.  When the Town received an administrative order to address copper and ammonia violations at the plant, they turned to Tata & Howard for assistance. We completed the design and construction of a Wastewater Treatment Facility Upgrade project which included the installation of an automated soda ash feed system and an integrated fixed film activated sludge system (IFAS). The IFAS system is an innovative biological treatment process using thousands of special carriers designed to increase total surface area for biofilm growth without expanding the plant’s footprint.  The blowers were also modified to provide better control over the aeration process.

A pilot study was conducted to test the ability of various reagents to facilitate the removal of copper from the waste stream.  An automated chemical addition system was designed to improve coagulation.  Additionally, a dynamic tangential filter was incorporated into the upgrade project.  These improvements have allowed the Town to now meet its discharge limits for ammonia and copper.

Water and Wastewater Engineering Services: Hydraulic Modeling, Facilities Plan, WRF Improvements, Goodyear, AZ

hydrant-flushing

Tata & Howard provided water and wastewater engineering services associated with the update of existing water and sewer system models using InfoWater and InfoSewer computer programs; review of the impact of proposed developments and proposed extensions to the City’s systems; verification of the hydraulic models for the City of Goodyear’s water distribution and wastewater collection systems. The water model included fire flow testing, C-value tests and calibration of the InfoWater hydraulic model. The wastewater collection system model included installation of six flow monitoring stations in three sub-basins, calibration of the model, development of a cost allocation model, and preparation of a technical report.

Tata & Howard prepared a facilities plan for the Corgett Water Reclamation Facility.  The plan addressed the need for process redundancy and recommended improvements for increased flows and Class A+ effluent.  Provided ongoing support services to address operational needs and to assess the impact of new developments on the system. Provided design, bidding, construction administration, resident observation, and construction services associated with improvements to the Corgett WRF including: filter system, low lift pump station, modifications to the sand filter, and instrumentation upgrades.

 

SaveSave

Water Storage Tank, Booster Pump Station, New Water Main, and Distribution System Upgrades, Spencer, MA

Town of Spencer, MA

SpencerMA water main

Tata & Howard provided construction administration services for a new 0.5 million gallon cast-in-place concrete water storage tank, booster pump station, approximately 12,600 linear feet of new 12-inch diameter water main, and miscellaneous distribution system upgrades. Construction of in-line isolation valves, removal of existing pressure-reducing valve (PRV) vaults, a new system wide SCADA system and new high lift pumps at the water treatment facility and well site were also included in Tata & Howard’s design. The purpose of this project is to separate the current single zone system into two pressure zones as required by an Administrative Consent Order from the MassDEP.

The creation of a two pressure zone system requires the replacement of the existing 200 horsepower (hp) pump at the Meadow Road Water Treatment Facility and 150 hp pump at the Cranberry Brook Well with lower head, high efficiency pumps and motors. The Meadow Road facility is the Town’s primary water supply source; therefore, changing of this pump requires coordination with the Department of Utilities and Facilities and the overall two pressure zone project construction sequencing to minimize the time this source is off-line.

Tata & Howard also verified the Town’s hydraulic model, which was used to select the best location for the new tank and select water main size for transmission and fire protection.  The model was also used to determine the boundary line between the two pressure zones.  A Capital Efficiency Plan™ is currently being prepared.  Assistance will be provided, as needed, for public education of the project and during Town meetings.  This project is being funded by the American Recovery and Reinvestment Act through the Massachusetts State Revolving Fund (SRF).  Due to an aggressive schedule required under the funding requirements, all design; permitting associated with planning, zoning, and wetlands; and project bidding were completed and approved within a six-month period.

Water Supply Division Sanitary Survey, Greensboro, VT

New England lake

Tata & Howard first assisted the District with responses to the Water Supply Division Sanitary Survey and then developed alternatives for the long term plan that would address all of the deficiencies and meet compliance with the Federal and State drinking water rules.

The issues were as follows:

  • Wooden roof over concrete storage tank
  • Inadequate disinfection system and metering of source
  • Inadequate system pressures at the highest points within the system
  • Water losses
  • Inadequate metering of sources of supply to the storage tank
  • Inadequate distribution piping for fire flows.

The solutions developed were as follows:

  • Design and installation of concrete precast cover on storage tank
  • Design of new building at storage tank with flow measurement and disinfection and better storage tank access for cleaning
  • Virtual abandonment of auxiliary springs and surface water emergency source
  • Design  of  water  main  replacement  to  meet  required  system  pressures  for compliance with the drinking water standards and rules
  • Locating, permitting and developing a new source of supply (well) to supplement the  existing  wells  and  virtually  eliminate  the  old  spring  sources  due  to  the potential for contamination that had occurred in the past.
  • Securing the maximum amount of grant funding available to the District at 45% with the remainder a low interest loan.

Water Supply Upgrades, Canaan, VT

Water Supply Upgrades

Canaan Fire Districts (FD) #1 and #2, Canaan, VT

canaan vt river

Tata & Howard provided engineering services associated with water supply upgrades for Canaan FD #1 & #2. These two districts are located about 1.5 miles apart, meet monthly, and have one operator. For FD#2, located in Beecher Falls, VT, Tata & Howard completed construction of a new  concrete storage tank, well upgrades, and  distribution system improvements including significant replacement of pipe. Tata & Howard was able to secure a 75% grant for the project which resulted in little impact to their water rates.

Fire District #2

FD#2 has 100 customers. The issues included inadequate system pressures, inadequate storage tank, inadequate disinfection system, and leaky pipes.

Tata & Howard developed solutions that included the following:

  • A new storage tank at an elevation that would eliminate all pressure issues
  • Distribution piping replacement and addition of hydrants of flushing and fire protection
  • Reduction in water losses allowing for reduced well pump size, resulting in lower annual power and chemical costs

Fire District #1 

FD#1 has two sources of supply. One is a large spring system located in Canada which consists of  ten springs connected together, all under the influence of surface water and the other is a high yielding well source in the town limits. The issues are inadequate spring source construction and ability to maintain, low system pressures across the State line (they provide water service to West Stewartstown, NH), inadequate flushing capabilities, inadequate distribution piping, high iron and manganese levels in well source, and inadequate storage tank.

The solutions include the following:

  • Elimination of the spring sources due to Canadian border issues and high cost for upgrading the springs and connection piping
  • Installation of filtration system to meet the standards for FE and MN
  • Construction of new larger water storage tank
  • Development of a second emergency supply
  • Improvements to distribution piping

In addition, we completed a feasibility study.