Mission Critical Storage Tanks, SLVHCS, New Orleans, LA

CLIENT: NBBJ, Columbus, Ohio

PROJECT: Mission critical storage tank systems for Southeast Louisiana Veterans Health Care System (SLVHCS)

hospital new orleans
SLVHCS in New Orleans, LA

THE CHALLENGE: SLVHCS is the successor to the VA Medical Center, which was decimated by Hurricane Katrina in 2005. The new hospital requirements included green building practices and resiliency during natural disasters, including the ability to remain operational for at least five days with enough provisions and accommodations for up to 1,000 staff and patients in case of a major disaster.

The atrium of Southeast Louisiana Veterans Health Care System
The atrium of SLVHCS

THE SOLUTION: Tata & Howard provided design and construction administration services on specific components of the mission critical storage tanks, which include a domestic water tank, sewage holding tank, cooling tower process and bleed water tank, and fire protection water tank. Our design of specific components of the mission critical tanks included coating, waterproofing, mixing, pumping, bacteria control, odor control, venting, piping to five feet outside the tanks, and instrumentation and control. Specific design elements for resiliency and green design included the following:

  • Domestic Water Tank system instrumentation/controls include storage tank level measurement and control of inlet/outlet valves. The system also includes ultraviolet disinfection of all potable water pumped from the storage tank into the hospital.
  • Sewage Holding Tank is waterproof and its control system to provide automated response to an event using electrically actuated valves that direct the sewage from the gravity system to the holding tank. After the event, the system will turn the pumps on and transfer the sewage to the City’s system. A water spray system will automatically wash down the empty tank.
  • Cooling Tower Make-up Water Tank is waterproof and its control system design provides electrically actuated valves to receive rainwater from the building roof drains, condensate from the buildings, and potable water from the City’s water system. The Cooling Tower Make-up system instrumentation/controls include tank level measurement and control of inlet/outlet valves.
  • Cooling Tower Bleedwater Tank is waterproof and its control systems design provides electrically actuated valves to accept water from the cooling towers, recycles water to the cooling towers, and pumps it into the municipal sewer system. The Cooling Tower Bleedwater Tank system instrumentation/controls will include tank level measurement and control of inlet/outlet valves.
  • Fire Protection Water Tank is waterproof and its control system design provides electrically actuated valves to automate control of receipt of water from the CEP/Warehouse roof drains and the City’s water system.
  • The instrumentation and controls for all of the above elements are capable of communicating with the facility ‘s SCADA system.

PROGRESS: The new state-of-the-art facility opened on August 1, 2015, and the building is on track to receive LEED silver certification. For comprehensive information on the new hospital, please click here.

Water Storage Tank Painting, Cleaning, and Rehabilitation, Worcester, MA

CLIENT: City of Worcester, Massachusetts

Chester Street 0.5 million gallon water storage tank in Worcester, MA

PROJECT: Chester Street 0.5 million gallon water storage tank painting, cleaning, and rehabilitation

THE CHALLENGE: The Chester Street water storage tank required evaluation, repair, cleaning, and painting of both the interior and the exterior. The tank is located in a heavily populated residential neighborhood and the exterior surface had high levels of lead in the paint. Therefore, special attention to lead contamination, noise, and construction debris was required. In addition, determination of the effects of taking the tank offline were required before any work could be started.

THE SOLUTION:  Analysis of the Super High Service Area using the verified hydraulic model was conducted, and the model was run under extended period simulation (EPS) to evaluate the potential pressure problems within the service area. As a result, operational modifications to the existing pump stations and service zones were recommended. Working only during daylight hours while keeping noise and debris to a bare minimum, construction crews completed miscellaneous repairs including replacing the anchor bolts, installation of overflow support brackets, modification of the access ladder, modification of the roof ladder, repair of the upper level sway rod, extension of the balcony handrail, installation of a roof handrail, and replacement of the roof finial vent. During the exterior abrasive cleaning, a containment system was utilized to prevent lead from getting into the air and soil. Once all repairs and cleaning were completed, the interior and exterior of the elevated tank were painted.

PROGRESS: Two years later, the tank is still in pristine condition, as shown in the photo above.

8.4 mgd Water Treatment Plant Design, Permitting, Construction Administration, Falmouth, MA

DAF water treatment plant

THE CHALLENGE: More stringent USEPA and MassDEP regulations, including Stage 2 Disinfectants/Disinfection-by-Product Rule (S2 D/DBPR) and the Long Term 2 Enhanced Surface Water Treatment Rule (LT2ESWTR), resulted in the Town of Falmouth needing to make a decision on whether to construct a filtration facility in compliance with the SWTR or to upgrade disinfection processes only at the existing Long Pond Water Treatment Facility (LPWTF) to maintain the existing Filtration Waiver.

THE SOLUTION: Because the existing LPWTF utilized no filtration to remove bacteria, organics, and particulates, the water quality entering the distribution system was an ongoing concern with elevated turbidity and organics leading to seasonal color, taste, and odor complaints; elevated bacteria and concentrations; and elevated algae counts. In addition, the high doses of chlorine needed to maintain the disinfection residuals required for an unfiltered supply reacted with the organics in the raw water to form disinfection by-products. Therefore, the only viable option for the Town of Falmouth was a new water treatment plant. After evaluating 22 treatment processes and developing eight treatment alternatives for pilot testing, only one treatment process met all goals: Dissolved Air Flotation (DAF) clarification, intermediate ozone followed by filtration. This alternative also scored favorably on the benefit/cost analysis.

Tata & Howard provided design and construction services for the new Dissolved Air Flotation (DAF) facility with a design capacity of 8.4 million gallons per day (mgd) for the Long Pond surface water supply for the Town of Falmouth, MA. The water treatment plant (WTP) utilizes coagulation, mixing, flocculation, dissolved air flotation (DAF), dual media filtration including granular activated carbon (GAC) above sand, chemical feed systems, and an intermediate ozone feed. Building components include HVAC, plumbing, fire sprinkler, gas and electrical services. Other work included site work with exterior piping systems, exterior above and below ground tanks, sludge holding lagoons, construction of a garage, new raw water intake and pump station, directional drilling of raw water mains, and demolition of equipment and site piping at the existing water treatment facility.

As part of the project, Tata & Howard provided design and permitting of a new 8.4 mgd intake and raw water pump station (RWPS) for the WTP.  The new intake and RWPS were constructed along the eastern shore of Long Pond and replaces the existing intake and Low Lift Pump Station.  The new intake and RWPS includes a two-level intake consisting of two 8.4 mgd rated intake screens installed at elevations -3 feet below mean sea level (MSL) and -13 feet below MSL.  The 36-inch HDPE intake pipeline connects the intake screens to the new RWPS located approximately 150 feet from the eastern shore of Long Pond.  An air burst system was designed in the RWPS to provide a means for routine cleaning of the new intake screens.

An accelerated 11 month design and permitting schedule, followed by contractor prequalification, bidding, and award, were completed in time to qualify the Town for >$3M in principal forgiveness.

Design included the following:
• 300 Drawings
• 1,200 pages of Specifications
• SRF PEF application
• Monthly project meetings
• Coordination with Building Department
• Coordination with Board of Health
• Coordination with Town IT Department
• Coordination with Police and Fire Departments
• Coordination with Gas and Electric Utilities

Permits included the following:
• Wetlands Protection Act-Local Conservation Commission
• Board of Health
• Remediation General Permit (NPDES)
• Massachusetts General Permit
• Environmental Notification Form
• Massachusetts Historical Commission: Intensive Archaeological Survey including 200 test holes
• MassDEP Approval to Construct WTP: BRP WS 24
• DWSRF PAC
• 401 Water Quality Certification
• NHESP – Turtle Protection Plan
• Chapter 91 Waterways License
• U.S. Army Corps of Engineers General Permit

The construction of the Long Pond Water Treatment Plant progressed on schedule and was completed in 2017.  dji_0051The plant included numerous sustainability and energy efficiency initiatives including the following:

  • Recycling spent backwash water to head of plant and back into the treatment process, after it passes through a plate settler to remove solids.
  • Recycling laboratory analyzer and filter influent piping gallery analyzer discharges back into the treatment process.
  • Using filter-to-waste water after a filter backwash sequence as supply water for the next backwash, instead of using finished water for backwashing.
  • Discharging cleaner supernatant water off the top of the lined lagoons to an unlined infiltration lagoon and back into the ground to minimize residuals.
  • Use of local/native plants for landscaping, including an irrigation system using collected rainwater from roof drainage.
  • Interior and exterior LED lighting fixtures.
  • Variable Frequency Drives (VFDs) on HVAC equipment and process equipment motors.

The plant went online on October 18, 2017. The work was funded under the SRF program. The Long Pond Water Treatment Plant received an ENR New England 2017 Best Project Award in the Water/Environment category, and an Associated Builders & Contractors of Massachusetts Eagle Award in the Public Works – Environmental category. For a drone video of the new water treatment plant taken by the general contractor, Methuen Construction, please see below:

SaveSave

SaveSave

SaveSave

Standpipe Rehabilitation, University of Southern Maine

USM standpipe rehabilitationTata & Howard provided engineering services to the University of Southern Maine related to the interior and exterior rehabilitation of a welded steel water storage tank. The standpipe was constructed in the 1950’s and is approximately 30 feet in diameter and 105 feet tall with a capacity of 0.55 million gallons. The scope of services included preparing Contract Documents for the cleaning, interior abrasive blasting, exterior pressure washing, and interior and exterior coating application.

The project also included coordination with two cellular companies and incorporation of corresponding design considerations into the Contract Documents. Additional design considerations included providing the USM logo on the tank exterior, repairing foundation cracks and gaps, extending the overflow pipe and installing a flapper, screen, and concrete splash pad, providing safety climb system for exterior access ladder, replacing the roof vent, and installing a new roof access hatch. Tata & Howard provided bid assistance, construction administration services, and full time construction observation. Since the standpipe is located on a college campus, the time frame for completion was limited to summer break, but the standpipe rehabilitation project was completed within budget and on schedule.

Standpipe Rehabilitation, Oak Bluffs, MA

Oak Bluffs Water District, Oak Bluffs, MA

Tata & Howard has provided engineering consulting services for the design, Contract Document preparation, and bid assistance to the Oak Bluffs Water District for the interior and exterior standpipe rehabilitation of the Alpine Avenue Standpipe. We are currently providing construction administration services for the rehabilitation project.

The standpipe has a capacity of 2.0 million gallon and is a welded steel standpipe constructed in 1983. Additional work included removal of a telemetry building attached to the standpipe and design of a precast concrete building to house a tank level transmitter and communications equipment. The standpipe houses cellular carrier equipment and other communications equipment that was considered throughout the design. The Oak Bluffs water system maintains only one water storage tank. To provide adequate storage throughout the completion of the rehabilitation project an interconnection with Edgartown was opened.

Tata & Howard, Inc. coordinated the interconnection opening with the Oak Bluffs Water District, the Edgartown Water Department, and the Massachusetts Department of Environmental Protection. Oak Bluffs is a community that experiences significant demand increases throughout the summer months, therefore there was a very short window for project completion because the limiting weather conditions and increased summer demands.  The project is currently on schedule and within budget.

Water Storage Tank, Booster Pump Station, New Water Main, and Distribution System Upgrades, Spencer, MA

Town of Spencer, MA

SpencerMA water main

Tata & Howard provided construction administration services for a new 0.5 million gallon cast-in-place concrete water storage tank, booster pump station, approximately 12,600 linear feet of new 12-inch diameter water main, and miscellaneous distribution system upgrades. Construction of in-line isolation valves, removal of existing pressure-reducing valve (PRV) vaults, a new system wide SCADA system and new high lift pumps at the water treatment facility and well site were also included in Tata & Howard’s design. The purpose of this project is to separate the current single zone system into two pressure zones as required by an Administrative Consent Order from the MassDEP.

The creation of a two pressure zone system requires the replacement of the existing 200 horsepower (hp) pump at the Meadow Road Water Treatment Facility and 150 hp pump at the Cranberry Brook Well with lower head, high efficiency pumps and motors. The Meadow Road facility is the Town’s primary water supply source; therefore, changing of this pump requires coordination with the Department of Utilities and Facilities and the overall two pressure zone project construction sequencing to minimize the time this source is off-line.

Tata & Howard also verified the Town’s hydraulic model, which was used to select the best location for the new tank and select water main size for transmission and fire protection.  The model was also used to determine the boundary line between the two pressure zones.  A Capital Efficiency Plan™ is currently being prepared.  Assistance will be provided, as needed, for public education of the project and during Town meetings.  This project is being funded by the American Recovery and Reinvestment Act through the Massachusetts State Revolving Fund (SRF).  Due to an aggressive schedule required under the funding requirements, all design; permitting associated with planning, zoning, and wetlands; and project bidding were completed and approved within a six-month period.

Water Supply Division Sanitary Survey, Greensboro, VT

New England lake

Tata & Howard first assisted the District with responses to the Water Supply Division Sanitary Survey and then developed alternatives for the long term plan that would address all of the deficiencies and meet compliance with the Federal and State drinking water rules.

The issues were as follows:

  • Wooden roof over concrete storage tank
  • Inadequate disinfection system and metering of source
  • Inadequate system pressures at the highest points within the system
  • Water losses
  • Inadequate metering of sources of supply to the storage tank
  • Inadequate distribution piping for fire flows.

The solutions developed were as follows:

  • Design and installation of concrete precast cover on storage tank
  • Design of new building at storage tank with flow measurement and disinfection and better storage tank access for cleaning
  • Virtual abandonment of auxiliary springs and surface water emergency source
  • Design  of  water  main  replacement  to  meet  required  system  pressures  for compliance with the drinking water standards and rules
  • Locating, permitting and developing a new source of supply (well) to supplement the  existing  wells  and  virtually  eliminate  the  old  spring  sources  due  to  the potential for contamination that had occurred in the past.
  • Securing the maximum amount of grant funding available to the District at 45% with the remainder a low interest loan.

Water Supply Upgrades, Canaan, VT

Water Supply Upgrades

Canaan Fire Districts (FD) #1 and #2, Canaan, VT

canaan vt river

Tata & Howard provided engineering services associated with water supply upgrades for Canaan FD #1 & #2. These two districts are located about 1.5 miles apart, meet monthly, and have one operator. For FD#2, located in Beecher Falls, VT, Tata & Howard completed construction of a new  concrete storage tank, well upgrades, and  distribution system improvements including significant replacement of pipe. Tata & Howard was able to secure a 75% grant for the project which resulted in little impact to their water rates.

Fire District #2

FD#2 has 100 customers. The issues included inadequate system pressures, inadequate storage tank, inadequate disinfection system, and leaky pipes.

Tata & Howard developed solutions that included the following:

  • A new storage tank at an elevation that would eliminate all pressure issues
  • Distribution piping replacement and addition of hydrants of flushing and fire protection
  • Reduction in water losses allowing for reduced well pump size, resulting in lower annual power and chemical costs

Fire District #1 

FD#1 has two sources of supply. One is a large spring system located in Canada which consists of  ten springs connected together, all under the influence of surface water and the other is a high yielding well source in the town limits. The issues are inadequate spring source construction and ability to maintain, low system pressures across the State line (they provide water service to West Stewartstown, NH), inadequate flushing capabilities, inadequate distribution piping, high iron and manganese levels in well source, and inadequate storage tank.

The solutions include the following:

  • Elimination of the spring sources due to Canadian border issues and high cost for upgrading the springs and connection piping
  • Installation of filtration system to meet the standards for FE and MN
  • Construction of new larger water storage tank
  • Development of a second emergency supply
  • Improvements to distribution piping

In addition, we completed a feasibility study.

Water Distribution System Study and Capital Efficiency Plans™

Aquarion Water Company
Areas of service: Oxford, Millbury, Hingham and Hull, MA and Hampton, NH

Aquarion_SuttonAve_Water_Tank

Tata & Howard has been providing general engineering services to the Aquarion Water Company in Massachusetts and New Hampshire for the last five years.  Our work has included the design of water mains and storage tanks, new source development, replacement well designs, hydraulic studies and Capital Efficiency Plans™.

As of 2019, We have completed or are currently completing Capital Efficiency Plans™ for each of the systems in Massachusetts and New Hampshire.  Within the two states, Aquarion Water Company operates a total of approximately 430 miles of water main.  Completion of the Capital Efficiency Plans™ has provided Aquarion with a basis for improvements throughout each of the systems.  The analysis not only reviewed hydraulic considerations but included a detailed analysis of assets and critical components.  By utilizing this approach, Aquarion Water Company was able to spend money effectively on upgrades to the system.

For example, as part of a hydraulic evaluation, it was recommended that Aquarion replace the water main on Mill Road to meet fire flow requirements in the eastern part of the system.  After consideration of the age, material, and break history of the surrounding water mains, it was determined that from a capital efficiency standpoint, replacement of the water main on Pine Road would benefit Aquarion more than replacement of the water main on Mill Road.

The water main on Pine Road had reportedly experienced numerous breaks and would eventually require replacement in the near future.  Installation of the water main on Pine Road allowed the Aquarion Water Company to meet the needed fire flow requirement, eliminate a problematic water main, and reduce the overall capital cost.  All the studies included an analysis of the existing supplies versus the estimated future demands as well as storage capacity.  The Hingham/Hull Water Distribution System Study included an analysis of potential water supply sources.  Tata & Howard evaluated the potential of connecting to MWRA, buying water from Cohasset and drilling new wells within the Town.  All options included potential costs for engineering, permitting and construction.

Tata & Howard completed a storage evaluation for the Hingham and Hull water systems.  The purpose of the evaluation was to determine if the Strawberry Hill Tank was needed.  Following a tank inspection, the tank was determined to be structurally deficient and needed substantial work to improve the integrity of the elevated tank.  The Strawberry Hill Tank had a capacity of 0.51 million gallons and had an overflow elevation that was approximately 20 feet lower than the Turkey Hill Tank located in the same service area.  The water in the Strawberry Hill Tank did not fluctuate and caused concern for contaminated water.  Based on a storage evaluation and hydraulic analysis, it was determined that the Strawberry Hill Tank was not needed.  The Aquarion Water Company subsequently removed the tank from the system.

Water Main, Pump Station, and Storage Tank, Athol, MA

AtholMA_tank_construction

Tata & Howard provided engineering services for a water main, pump station, and storage tank for Athol Economic Development. The project specifically included the design of a new booster pump station with a chlorine injection system, emergency generator, SCADA, approximately 3,800 linear feet of 12-inch diameter water main, and a new 210,000 gallon elevated water storage tank on Templeton Road.  This project is an extension to the existing water distribution system and was designed to serve an area of commercial development, including a Market Basket, along Route 2A.